This page is a commissioning gate: a simple, auditable way to decide whether a Kristal Farms site is ready to move from “build” to “operate.”
A Go is not optimism. It is evidence that the system can run safely, compliantly, and legitimately, including when conditions degrade.
How to use this checklist
Each item is pass/fail with required evidence.
If any No-Go item fails, you either:
delay launch, or
operate in a reduced mode that stays inside constraints (never “ship now, fix later” on safety/compliance).
The goal is a site that can be trusted by:
the community,
the operator,
tenants,
and regulators.
Minimum Go (Phase 1 readiness)
The minimum standard
You can launch Phase 1 when the site can reliably deliver compute, heat recovery, and connectivity
while proving environmental compliance and governance legitimacy.
Go / No-Go gates
1) Community legitimacy (non-negotiable)
Consent + benefit agreement executed
Signed agreements are in place (community benefit, local priorities, dispute mechanisms).
Evidence required
Signed agreements and governance charter
Defined community services (heat endpoints, connectivity commitments where applicable)
Named liaisons and escalation path
Operating boundaries agreed
Clear limits on what the operator can and cannot do/see (tenancy boundaries, privacy, monitoring scope).
Evidence required
Tenancy model + monitoring policy (black-box boundary)
Site access policy (roles, approvals, logs)
Incident response commitments (who is contacted, when, and how)
2) Site, safety, and compliance
Safety systems commissioned
Fire safety, emergency procedures, and physical security are tested and documented.
Evidence required
Commissioning reports (fire suppression, alarms, egress, power cutover)
Emergency response plan + drill record
Physical security plan (perimeter, cameras, access control, visitor process)
Environmental controls proven
Monitoring is live, thresholds are enforced, and compliance-first behavior is demonstrated.
Evidence required
Monitoring plan (temperatures, discharge limits, flow, alarms)
Proof of compliance operating modes (load shedding / mode switching)
Incident runbooks and escalation path for environmental events
3) Power & grid readiness
Power handoff commissioned
The site has stable power with metering, protection, and documented start/stop sequencing.